Club Redevelopment Timeline Guide

A board-ready way to plan the phases, dependencies, decisions, and schedule risks in a NSW club redevelopment.

Build a Timeline the Board Can Rely On

Download the full guide below, or read the phase-by-phase breakdown further down the page.

Download as PDF

Enter your details to download the complete Club Redevelopment Timeline Guide as a printable PDF.

No spam. We'll only email you about club redevelopment resources.

A useful programme connects your target opening date with the decisions, approvals, design, procurement and handover needed to reach it. A refurbishment in an operating club can follow a different sequence from a new extension, even with a similar budget.

This guide explains the main phases, what needs to happen before each can start and where the board can help keep things moving. Your project team can then build a dated programme around the club’s scope, site, approvals and operating needs.

What to ask your team:

For each milestone, show who is responsible, what needs to happen first and when the board needs to decide. Identify the critical path: the connected tasks that determine the finish date. Keep authority response times and other uncertain items visible in the programme.

Related reading: our Development Planning & Approvals service, and DA Approval Process for Club Redevelopment NSW.

1

Feasibility Study

Set around the board decision cycleSchedule pressure: Unclear brief or approval path

What Happens

  • Confirm the problem, desired outcome, project constraints, and decision owner
  • Site analysis — existing conditions, utilities, constraints documented
  • Test one or more concept directions against the operational brief
  • Ask the quantity surveyor (QS) to prepare an early cost plan with its assumptions and exclusions visible
  • Test funding, revenue, disruption, and affordability assumptions
  • Map the approvals, procurement path, dependencies, and decision dates
  • Governance structure options — steering committee, reporting, decision-making
  • Board decision: proceed to detailed design or pause/revise concept

Common Delays

  • The next board or committee meeting falls after the team needs a decision
  • The brief changes while options are being tested
  • Site analysis incomplete — utilities not fully mapped, asbestos survey deferred
  • Consultant scopes overlap or leave gaps
  • Member consultation deferred — board wants concept finalized first
  • Financial assumptions are not agreed or sensitivity-tested
2

Concept Design

Plan around option testing and consultationSchedule pressure: Late feedback or unresolved priorities

What Happens

  • Architect develops the preferred concept to an agreed level of detail
  • Schematic design drawings — floor plans, elevations, 3D renders
  • Schematic specifications — material types, finishes, key systems
  • QS updates the cost plan and records design assumptions and exclusions
  • Utility requirements confirmed — power, water, sewer, communications
  • Heritage advice and authority engagement arranged where applicable
  • Member consultation — concept presented, feedback collected, refinements made
  • Preliminary planning assessment — town planner advises on likely development application (DA) requirements
  • Board decision: approve concept, proceed to detailed design, or revise

Common Delays

  • Consultation requires further options or a revised brief
  • Heritage advice identifies design work or further investigation
  • Utility capacity or upgrade requirements remain unconfirmed
  • Board and member feedback arrives in separate revision cycles
  • Funding discussions wait for firmer scope or cost information
  • Planning advice identifies a constraint that changes the concept
3

Detailed Design & Documentation

Depends on coordination and design freezeSchedule pressure: Scope movement or consultant gaps

What Happens

  • Architect develops the design to the agreed documentation milestone
  • Detailed drawings produced — architectural, structural, mechanical, electrical, hydraulic
  • Detailed specifications — materials, finishes, quality standards, performance requirements
  • Applicable sustainability requirements confirmed with the design team
  • Accessibility and building-code advice incorporated for the current design
  • Engineering design completed — structural, mechanical, electrical, hydraulic systems
  • QS updates the cost plan against the coordinated design
  • Gaming venue compliance review — Liquor & Gaming NSW preliminary consultation if required
  • DA application package compiled
  • Project Manager appointed; baseline schedule developed

Common Delays

  • Architect and engineer information is issued on different assumptions
  • Sustainability, accessibility, or building-code advice requires design changes
  • Heritage requirements require further design development
  • Utility provider information is outstanding
  • Gaming or liquor requirements are not resolved for the proposed works
  • The updated cost plan exceeds the approved budget and scope must be reviewed
  • New requests continue after the agreed design-freeze date
  • Design freeze discipline not enforced — design continues past intended freeze date

Board Warning

Treat design freeze as a board decision gate. Record what is approved, what remains provisional, and how later changes affect cost and program.

4

Development Application (DA) Lodgement & Determination

Authority-led; confirm the current pathwaySchedule pressure: Information requests or design amendments

What Happens

  • Pre-lodgement engagement considered with the planning team
  • DA application submitted to local council
  • Council completeness review — checks if all documentation provided
  • If incomplete: RFI (Request for Information) issued
  • Notification or referral steps completed where required for the application
  • Assessment against the planning controls and matters relevant to the site
  • Draft or final conditions reviewed for delivery implications
  • Development Consent issued with conditions

Common Delays

  • The application is missing information or relies on unresolved consultant inputs
  • Submissions raise noise, parking, privacy, heritage, or operational issues
  • The consent authority requests amendments or additional information
  • Traffic, parking, heritage, environmental, or contamination work needs expansion
  • External referrals or utility advice sit outside the project team’s control
  • Proposed conditions affect staging, cost, or operations and need review
  • A review or appeal pathway is considered and requires separate advice

Board Warning

Do not promise a determination date from a generic allowance. Ask the planner to map the current pathway, information dependencies, authority steps, and a range of scenarios for this site.

5

Construction Documentation & Tender

Depends on document readiness and approvalsSchedule pressure: Incomplete scope or slow clarifications

What Happens

  • Consultant team completes the agreed tender documentation package
  • Specifications and performance requirements are coordinated with the drawings
  • QS prepares the agreed pricing schedule or bill of quantities
  • PM maps tender, evaluation, approval, negotiation, and mobilisation decisions
  • Tender documentation compiled — drawings, specs, BoQ, contract terms, site information
  • Tender package released to the approved shortlist
  • Tenderers inspect the site, ask questions, and prepare compliant submissions
  • Tender evaluation, board approval, contract negotiation and signature

Common Delays

  • Tender documents are issued with unresolved design or scope items
  • Pricing schedules cannot be completed because consultant information is missing
  • Tender questions reveal conflicting drawings, specifications, or site information
  • Tenders contain material qualifications or cannot be compared like for like
  • Preferred-tenderer clarifications change price, program, or risk allocation
  • Legal review, funding conditions, or board formalities are not programmed

Board Warning

Illustrative tender planning example only: four weeks for tenderers plus two weeks for evaluation, clarifications, and the board decision equals six weeks from issue to decision. That example assumes the documents, shortlist, evaluation plan, and meeting date are ready. If tasks overlap, show the dependency rather than counting the same time twice.

6

Construction

Set from the accepted contractor programSchedule pressure: Critical-path change or unresolved access

What Happens

  • Site establishment, access controls, temporary facilities, and operational separation
  • Demolition and hazardous-material controls where required
  • Structure, envelope, and services delivered in the agreed sequence
  • Fitout, specialist equipment, testing, and commissioning coordinated
  • Staged handovers managed around club operations where applicable
  • Completion evidence, training, manuals, approvals, and defects documented

Common Delays

  • Weather affects critical external or structural activities
  • Long-lead items are selected or released later than the procurement schedule requires
  • Trade resources or key site personnel are not available as programmed
  • Design information or approvals are issued after the work is due to start
  • Variations change the critical path or require rework
  • Ground, utility, hazardous-material, or contamination conditions differ from the tender information
  • Operational staging, shutdowns, member access, or temporary works are not resolved
  • Testing, commissioning, certification, or handover evidence is incomplete

Board Warning

Use the accepted baseline as the control document. Require each update to show actual progress, critical-path movement, approved changes, recovery actions, and decisions needed from the club.

Construction Program Inputs to Test

Project conditionWhat changes the programEvidence to requestAllowance treatmentDecision gate
Operating clubMember access, trading hours, noise and shutdown windowsStaging and temporary-works planTest each handover and shutdown dependencyBoard accepts the operational impact
Existing buildingServices, structure, hazardous materials and concealed conditionsSurveys and investigation registerKeep unresolved conditions visible in the risk allowanceTenderers price the same information
Specialist equipmentLifts, kitchens, HVAC, electrical upgrades and venue systemsProcurement schedule with decision datesTrack design release, manufacture, delivery and commissioningOrders align with the critical path
Authority interfacesConsent conditions, utilities, inspections and certificationResponsibility matrix and approvals scheduleSeparate team-controlled tasks from external response timesNo milestone relies on an unnamed approval
Board decisionsScope, budget, funding, contract departures and change requestsDecision calendar with papers issued in advanceEscalate decisions before they reach the critical pathDelegations and meeting dates are confirmed

These checks help the team build a project-specific baseline. They do not replace the contractor’s detailed program, consultant advice, authority information, or the executed contract.

7

Defects Liability Period

Use the period in the executed contractSchedule pressure: Slow close-out or unclear responsibility

What Happens

  • Building occupied and operations commence
  • Defects discovered post-opening identified and logged
  • Builder rectifies defects in accordance with the executed contract
  • Security, retention, and release steps administered under the contract
  • Defects tracked with owner, due date, access needs, evidence, and status
  • Final inspection and close-out planned before the contractual period expires
  • Security released only through the contract’s agreed process

Common Delays

  • Builder slow to respond to defect notices
  • Disputes over whether item is "defect" or "maintenance"
  • Defect rectification poor quality — requires re-work
  • Close-out actions are left until the end of the contractual period
  • Responsibility for later issues is assumed without checking the contract and relevant advice

Phase and Decision-Gate Summary

Use this sequence to test whether the next phase is genuinely ready to start. Some work can overlap, but overlapping unresolved scope or approvals can simply move risk into tender or construction.

PhasePlanning basisGate to pass
Feasibility StudyTest the case for changeBoard endorses the brief and next-stage budget
Concept DesignCompare options and impactsBoard selects a preferred concept
Detailed DesignCoordinate scope and costDesign freeze and cost plan approved
DA Lodgement & DeterminationAuthority timing depends on the site, proposal, information quality, referrals, and submissionsFollow the project-specific authority pathwayConsent pathway and delivery conditions understood
Construction Documentation & TenderComplete the package and compare tendersBoard approves a value-for-money recommendation
ConstructionBuild the baseline from the actual scope, staging, procurement, access, and approval dependenciesManage the accepted contractor programPractical completion evidence accepted
Defects LiabilityUse the executed contract periodDefects and close-out obligations resolved

Scope gate

Brief approved

Outcomes, constraints, budget, and governance aligned

Approval gate

Pathway mapped

Information, referrals, and conditions understood

Delivery gate

Baseline accepted

Scope, staging, procurement, and handover are programmed

Use ranges as scenarios, not promises

Ask the team for a base case, a credible downside case, and the assumptions behind each. When an assumption changes, update the forecast and record the board decision required. A generic percentage allowance can hide the dependency that actually needs action.

Ten Schedule Risks to Review

Review these risks across the full project lifecycle. Their priority and effect will differ by project.

1

Approval pathway changes

Maintain an approvals schedule and information register

Objections, RFI, heritage issues, council review prolonged.

2

Design decisions move

Set decision dates and record the effect of late changes

Scope changes, client decisions delayed, cost control issues, design coordination.

3

Construction Material & Labour Issues

Track release, manufacture, delivery, access, and installation

Long-lead items delayed, trades unavailable, labour shortages.

4

Site Conditions Worse Than Anticipated

Investigate early and state the residual assumptions in the tender

Geotechnical surprises, utility conflicts, contamination discovered.

5

Weather Events

Link allowances to weather-sensitive critical activities

Rain, extreme weather, seasonal delays.

6

Slow change control

Assess time and cost before directing changed work

Uncontrolled variations, design changes, scope creep.

7

Staging & Phasing Complexity

Make staging part of the baseline, not a side plan

Operational access, temporary works, shutdowns, and handovers are not coordinated.

8

Regulatory Approval & Inspection Delays

Name the owner, notice period, prerequisites, and evidence for each step

Council building inspections late, compliance issues requiring re-work.

9

Unclear team responsibilities

Use a responsibility matrix and one controlled decision log

Architect/builder/PM coordination failures, unclear responsibilities, slow decision-making.

10

Contingency Underestimation

Review remaining float and risk allowance at each reporting cycle

Insufficient contingency allocated; unforeseen issues consume contingency quickly.

How to Minimise Delays

Disciplined project management makes emerging delay visible early enough for the board and project team to act.

Front-load decision-making

Complete feasibility, concept, and design phases comprehensively. Avoid design changes during construction.

Plan a comprehensive DA strategy

Early council engagement, heritage assessment, objection management, and appeal contingency included in the timeline.

Enforce design freeze discipline

No scope changes after freeze date without formal change control and explicit timeline acceptance.

Allocate realistic contingency

Set allowances from the project risk register and accepted program. Focus management on critical activities and near-critical paths.

Procure long-lead items early

Identify lifts, gaming machines, HVAC units, and kitchen equipment early. Place orders and manage delivery schedules.

Appoint experienced project team

PM with similar project experience, QS with cost control discipline, site management with scheduling discipline.

Weekly site meetings during construction

Track progress weekly against schedule. Identify delays early. Implement corrective action promptly.

Monthly board reporting

Track schedule variance monthly. Escalate delays to board. Decision on acceleration strategies (overtime, extra resources).

Download as PDF

Enter your details to download the complete Club Redevelopment Timeline Guide as a printable PDF.

No spam. We'll only email you about club redevelopment resources.

Need a Timeline Specific to Your Project?

Site constraints, approvals, staging, procurement, and club operations shape the program. We can help your board turn those dependencies into a practical, project-specific schedule.